Full-size well drilling drives geothermal plant capital cost

July 2025, 1 year ago. Geothermal energy, physical constraint.

  • Source2025 Geothermal Drilling Cost Curves Update
  • AuthorsDayo Akindipe and Erik Witter
  • DateJuly 2025, 1 year ago
  • FieldGeothermal energy
  • KindPhysical

Based on internal analysis carried out by the National Renewable Energy Laboratory (NREL), drilling full-size wells for both resource confirmation and field development currently accounts for 30% to 57% of the overnight capital cost to install a new plant.

Source: 2025 Geothermal Drilling Cost Curves Update (2025).

A 2025 National Renewable Energy Laboratory update reports that drilling full-size wells for resource confirmation and field development accounts for 30% to 57% of the overnight capital cost of a new plant. The figure comes from NREL internal analysis.