Regulatory
1 current regulatory constraints.
- Interconnection to operation now takes 55 months for new power projectsA 2025 Berkeley Lab report says the typical project built in 2024 took 55 months from interconnection request to commercial operations. That compares with 36 months in 2015 and 22 months in 2008.Electric grid · Regulatory · December 2025, 11 months ago