Interconnection to operation now takes 55 months for new power projects
December 2025, 11 months ago. Electric grid, regulatory constraint.
The typical project built in 2024 took 55 months from the interconnection request to commercial operations, compared to 36 months in 2015 and 22 months in 2008.
Source: Queued Up: 2025 Edition, Characteristics of Power Plants Seeking Transmission Interconnection As of the End of 2024 (2025).
A 2025 Berkeley Lab report says the typical project built in 2024 took 55 months from interconnection request to commercial operations. That compares with 36 months in 2015 and 22 months in 2008.