Supply
2 current supply constraints.
- Copper supply gap persists in 2030 despite high mined outputThe IEA's Global Critical Minerals Outlook 2024, published in May 2024, reports that even in a high production case with almost 2 Mt of extra mined supply, a 2.2 Mt (10%) gap remains against demand from government climate pledges. It also reports a 4.5 Mt (20%) shortfall against the NZE Scenario in 2030, and stresses the long lead times for new production.Critical minerals · Supply · May 2024, 2 years ago
- Large power transformer lead times of 36 to 60 monthsA 2024 U.S. Department of Energy report to Congress says lead times for acquiring a large power transformer are commonly quoted at 36 months. Maximum lead times reach as much as 60 months.Electric grid · Supply · July 2024, 2 years ago