Electric grid
3 current bottlenecks in this field.
- Interconnection to operation now takes 55 months for new power projectsA 2025 Berkeley Lab report says the typical project built in 2024 took 55 months from interconnection request to commercial operations. That compares with 36 months in 2015 and 22 months in 2008.Electric grid · Regulatory · December 2025, 11 months ago
- Large power transformer lead times of 36 to 60 monthsA 2024 U.S. Department of Energy report to Congress says lead times for acquiring a large power transformer are commonly quoted at 36 months. Maximum lead times reach as much as 60 months.Electric grid · Supply · July 2024, 2 years ago
- Grid power for large data centers can take 4 to 5+ yearsA 2026 source reports that building a data center typically takes 18 to 36 months. It says growing interconnection queues and processing backlogs can mean powering the site from the grid often takes 4 to 5 or more years.Electric grid · Physical · March 2026, 8 months ago